Every BOP pressure test stops the well for 6 to 12 hours. On a 14-day cycle, that's roughly 26 tests a year per rig. Move to 21 days and you drop about nine of them.

Aquila built the first approved move from 14 to 21 days. Here is what BSEE asks for, what it's worth, and how to tell if your rig is ready.

blog card

Why 21 days is not a safety trade-off

- The 14-day US rule was the outlier. API Standard 53 already sets 21 days as the industry standard used worldwide.

- Testing too often wears the BOP. BSEE-funded research by Argonne National Laboratory found that wellbore-sealing elastomers on pipe rams, VBRs and annulars have a higher probability of failure on demand under 14-day testing than under 21-day testing.

- Most failures are driven by events, not time. The same study concluded that extending the interval has minimal impact on component reliability.

- The industry savings are large. Argonne estimated about $410 million a year in industry-wide savings at a 21-day interval.

What BSEE actually requires: the four-part BOP health monitoring plan

Under 30 CFR 250.737(a)(4), an operator can ask the BSEE Regional Supervisor, District Field Operations, to approve a 21-day BOP testing frequency instead of the 14-day schedule. BSEE approves the request if the BOP health monitoring plan follows recognized engineering practice and includes all four of these elements:

BSEE requirement What it means on the rig How Aquila delivers it
1. Condition monitoring Continuous surveillance of BOP control system sensor readings, real-time condition analysis and displays, functional pressure signal analysis, and historical sensor data Real-Time Monitoring (RTM) and Oculus; the DBA edge kit for rigs without data infrastructure
2. Failure propagation analysis A model showing how one component failure propagates to the loss of a barrier function Engineer-built BOP fault tree models
3. Failure tracking and resolution Detailed failure reports and identification of recurring problems Failure tracking and trending in Oculus
4. Quarterly reports The data from items 1–3, submitted to BSEE every quarter Aquila quarterly BOP reliability reports

Two details matter after approval:

  • Shear ram function tests can also move to every 21 days under the terms of the approval.
  • The District Manager can still require more frequent testing if conditions or BOP performance warrant it. Approval is not a one-time filing. The monitoring has to keep working every day after it.

What 21 days is worth per rig

 14-day interval21-day interval
BOP pressure tests per year~26~17
Tests avoidedn/a~9
Rig time recovered (6–12 hours per test)n/a54–108 hours (2.3–4.5 rig days)

Example: at a $500,000 per day spread rate, 2.3 to 4.5 rig days is worth about $1.1 million to $2.3 million per rig per year.

Use your own numbers: annual value = 9 tests × hours per test ÷ 24 × daily spread rate.

The benefits go beyond rig time:

  • Fewer pressure cycles on the sealing elastomers.
  • Fewer high-pressure operations and system reconfigurations on deck.
  • Less test-related paperwork and scheduling disruption.

How the first 14→21 approval was built

Aquila delivered the industry's first approved move from 14 to 21 days by combining engineering analysis with digital assurance. That meant continuous real-time BOP monitoring, engineer-built failure models, and a documented failure tracking and reporting process: the same four pillars the rule asks for. 

That work is backed by more than five years of real-time BOP monitoring in the Gulf. 

Norway is next

Norway is preparing its own move to 21-day BOP testing. Operators and drilling contractors on the Norwegian shelf will face the same question: can you prove BOP health continuously, not just every two weeks? 

The rigs that have monitoring, failure models and reporting in place before the rule lands will capture the savings first.

Is your rig ready for 21 days? A 5-question check

1. Are your BOP control system sensor readings streamed and watched continuously?

2. Do you have a failure propagation model (fault tree) for your specific stack?

3. Are failures logged with root cause and trended for recurrence?

4. Can you produce a quarterly BOP health report without a manual scramble?

5. Do the operator and drilling contractor agree on who owns the data and the filing?

If you answered no to any of them, that is the gap between your rig and 21 days.

Book a 21-day readiness review. In 30 minutes, an Aquila BOP reliability engineer will map your rig against the four BSEE requirements and estimate what 21 days is worth at your spread rate.

Frequently asked questions


Is 21-day BOP testing allowed in the US?

Yes. The 2019 Well Control Rule, effective July 19, 2019, kept the 14-day requirement but lets operators request a 21-day frequency under 30 CFR 250.737(a)(4).
 

Who submits the request?
The operator submits it to the BSEE Regional Supervisor, District Field Operations. In practice the drilling contractor supports it, because the BOP data sits with the rig.
 


What does the BOP health monitoring plan need to include?

Four elements: condition monitoring, failure propagation analysis, a failure tracking and resolution system, and quarterly reports to BSEE.
 


Is 21-day testing less safe than 14-day testing?

BSEE-funded Argonne research found minimal impact on component reliability, and a higher failure-on-demand probability for sealing elastomers under 14-day testing than under 21-day testing.
 


Can shear ram function tests move to 21 days too?

Yes, under the terms of an approved 21-day frequency.
 

Can BSEE take the 21-day approval back?
The District Manager can require more frequent testing if conditions or BOP performance warrant it, so continuous monitoring and quarterly reporting have to be maintained.
 